Dedicated Project Management & Technical Team
For a complex installation, working and coordinating with several organisations to ensure a safe and efficient event activation and demobilisation, the HIMOINSA Team assigned a dedicated project management and technical team. The team of six provided continuity of service and resources during each stage of the event organisation, activation and decommissioning.
In preparation for the event, weekly stadium visits were conducted to meet with SARES and the City of Cape Town to plan the site requirements, unit placement and cable runs, all of which were subject to change as sponsors and suppliers came on board.
Time management and organisation was critical. The stadium could only be accessed six days prior to the Tournament. Generators were an essential, heavy, large load equipment which required early placement on crane trucks before other vendors, who were also on a tight timeline. The team scheduled effectively and factored in contingency planning, successfully avoiding delays and safety risks. This was in fact proven to be needed, as there were high winds and storms in Cape Town the weekend before the event, but the contingency plans were activated immediately which avoided any installation delays.
After 2,400m of cable, fifteen generators and six lighting towers were successfully placed, two days of testing and commissioning were carried out, after which time changes could not be made.
During the three day event, the team were on site monitoring the units in person and remotely at all times. Technicians were stationed at the generator sites with runners and Project Management overview of all generators and Lighting Towers.
After the tournament, three days of decommissioning followed before the next event at the stadium was scheduled to take place.
A full project post-event debriefing took place with SARES and the HIMOINSA Southern Africa Project Management and Technical Teams to ensure that the solution and service received achieved the operational and financial results and efficiencies required for the event. and commissioned a fully functioning power plant within three weeks of the site being ready.